Current progress…Jubilee House Site Information Notice Board

Here’s an update on current progress from Conlon:

  • Demolition of existing roof structures should be complete in the next month (sorry for the noise!);
  • We are still working hard behind the scenes on the new design of the envelope cladding and 3rd floor steelwork.
  • The erection of the steel on the roof will be done in 5 phases, working from east to west.
  • We have commenced Phase 1 of the steelwork and will progress the other phases during the coming month.
  • The envelope cladding rails and window angles along the building adjacent to the road has commenced.
  • The damp proof membrane for the walls and windows with be stitched in place next month.
  • Cladding and window installation is programmed to follow thereafter.
  • Inside the building new floors are being laid and work continues on the electrical and mechanical infrastructure.

For more information speak to the Site Manager, Gordon MacKenzie/Kevin Meadows or contact Conlon’s head office on 01772 335268.

Introducing JMC…

On Monday, 10th March, JMC, our new IT Service provider visited Jubilee House.

JMC will be working with Danbro to develop our systems and transfer our IT provision as seamlessly as possible into the new building.  This was their first visit to Jubilee House to get a feel for the project, our vision and what’s involved.

Here they are all appropriately kitted out for the tour of the building (and a lovely sunny day as well!).

From left to right:  Craig (Danbro), Katie (Danbro), Hugh Houlston, Peter Wilson (both JMC), Ed (William Clark), Damian (Danbro).

From left to right: Craig (Danbro), Katie (Danbro), Hugh Houlston, Peter Wilson (both JMC), Ed (William Clark), Damian (Danbro).